Worked example · one fictional culvert
One fictional culvert, carried from a site visit to a signed report and certificate — every output shown, every figure checkable with a pencil.
Nine outputs, each on a sheet below.
Shown on nine sheets below, in the order a report carries them. Everything is one fictional culvert, carried from one site visit to a signed report and certificate.
Condition inspection report — worked example
CU-014 · Wadi crossing culvert · two-cell reinforced concrete box · 2 × (3.0 × 2.4) m cells · 18.0 m barrel
Output 01 · structure inventory
Every quantity has a source: the as-built drawing, or a measurement taken on site.
The inventory pass walks the structure from the road level over the culvert to the inlet and then the outlet. Dimensions are read from the as-built set and checked by tape and laser on site; where the two differ, the site figure governs and both are recorded. What could not be reached is written down before anything is rated: the inlet apron lay under sand and three metres of cell 2 stood under approximately 0.4 m of standing water.
Identification
Configuration
| Element | Quantity | Measured as | Source |
|---|---|---|---|
| Barrel, both cells | 36.0 m | 18.00 m × 2 cells, length along flow | AB-014 sh. 3 · tape 18.02 m |
| Headwalls | 55.76 m² | 2 × (8.20 × 3.40 m), exposed face | AB-014 sh. 4 · tape, agrees |
| Wing walls A–D | 46.80 m² | 4 × (4.50 × 2.60 m), mean height | laser, on site · AB-014 sh. 4 |
| Apron slabs | 65.60 m² | 2 × (8.20 × 4.00 m) | AB-014 sh. 3 · outlet taped; inlet under sand |
| Embankment slopes | 120.0 m² | 2 × 60 m², protected slope | AB-014 sh. 5 · paced on site |
| Wearing surface over | 468.0 m² | 26.0 m carriageway × 18.0 m | AB-014 sh. 2 |
Quantities are estimated from the as-built drawings and confirmed or corrected by site measurement, and the report says which. A quantity with neither source is not printed.
Output 02 · defect log and sketch
Every defect is located on the sketch, measured on site, and tied to the plate that shows it.
| Ref | Element · location | Defect | Length | Width | Quantity | State | Prio. | Plate |
|---|---|---|---|---|---|---|---|---|
| D-01 | Barrel · cell 1 soffit, ch. 4.2–9.6 | Cracking, transverse, 0.4 mm gauge | 5.40 m | — | 5.40 m | CS2 | Low | 25-118 |
| D-02 | Barrel · cell 1 soffit, ch. 7.8 | Spalling to reinforcement | 0.95 m | 0.40 m | 0.38 m² | CS3 | High | 25-121 |
| D-03 | Barrel · within D-02 | Exposed reinforcement, 2 bars, no section loss recorded | 0.84 m | — | 0.84 m | CS3 | High | 25-121 |
| D-04 | Barrel · cell 2 wall, joint J3, ch. 11.2–13.4 | Efflorescence at construction joint | 1.80 m | 0.60 m | 1.08 m² | CS2 | Low | 25-126 |
| D-05 | Headwall · junction with wing wall C, outlet | Joint sealant loss | 1.10 m | — | 1.10 m | CS2 | Medium | 25-133 |
| D-06 | Barrel · cell 2 invert, ch. 15.0–18.0 | Not assessed — submerged, approx. 0.4 m | 3.00 m | — | — | — | — | none |
| D-07 | Apron slab · inlet | Sand accumulation, 0.30 m deep; slab beneath not assessed | 8.20 m | 4.00 m | 9.84 m³ | — | Service | 25-104 |
| D-08 | Embankment · inlet, left of wing wall A | Erosion of slope protection | 3.00 m | 2.00 m | 6.00 m² | CS2 | Low | 25-109 |
Length and width are taken on site by tape; crack width by gauge. Quantity is length × width where both apply, and the unit follows: metres for a line, square metres for an area, cubic metres where a depth was measured (D-07). D-02 was proposed from the plate at 0.41 m² and corrected by the engineer to the taped 0.38 m²; the proposal is kept beside the correction, not overwritten.
Plate 25-121 · cell 1 soffit · ch. 7.8 · D-02, D-03
Photograph withheld. ISNAD does not publish an owner’s images — not in a specimen, not in marketing, not anywhere outside the owner’s own record. What leaves the instrument is the citation: plate, element, chainage, region, and the measurement it supports.
Output 03 · element condition table and structure condition index
The calculation is printed in full, so the index can be checked from the table that produced it.
Barrel · CS3 poor 1.2 m · CS4 severe 0.0 m, drawn at zero width rather than omitted · after the gap, hatched: not assessed 3.0 m
Barrel, reconciled to the logD-01 runs 5.40 m. The 1.20 m length containing D-02 and D-03 is taken at CS3, so D-01 contributes 4.20 m to CS2 and no length is counted twice; D-04 adds 1.80 m at CS2. Assessed 33.0 m: CS1 25.8, CS2 6.0, CS3 1.2. The states sum to the assessed quantity, never to the element total.
| Element | CS1 | CS2 | CS3 | CS4 | WCS | ESCI | Si | Si × ESCI |
|---|---|---|---|---|---|---|---|---|
| Barrel | 78.2 % | 18.2 % | 3.6 % | 0.0 % | 1.254 | 91.5 % | 4.0 | 366.0 |
| Headwalls | 96.1 % | 3.9 % | 0.0 % | 0.0 % | 1.039 | 98.7 % | 2.0 | 197.4 |
| Wing walls A–D | 100.0 % | 0.0 % | 0.0 % | 0.0 % | 1.000 | 100.0 % | 1.0 | 100.0 |
| Apron slabs (outlet assessed) | 100.0 % | 0.0 % | 0.0 % | 0.0 % | 1.000 | 100.0 % | 1.0 | 100.0 |
| Embankment slopes | 95.0 % | 5.0 % | 0.0 % | 0.0 % | 1.050 | 98.3 % | 1.0 | 98.3 |
| Wearing surface | 100.0 % | 0.0 % | 0.0 % | 0.0 % | 1.000 | 100.0 % | 1.0 | 100.0 |
| Σ | 10.0 | 961.7 | ||||||
| Structure condition index | SCI = Σ(Si × ESCI) / ΣSi = 961.7 / 10.0 | 96.2 % | ||||||
Output 04 · structure rating and component rating
Two ratings from one evidence base — and the rule that produced each, quoted.
96.2%
Structure condition index · band
Very good
Band 90–100 in the method’s rating table: minor defects in secondary elements; routine maintenance. The barrel’s spall is inside that band because its extent is 3.6 % of the assessed length.
6
NBI item 62 — culvert · component rating
Satisfactory
“Structural elements show some minor deterioration.” Governed by the worst significant defect, not by its extent: exposed reinforcement holds the item at 6 under rule CS-3(b).
Rule CS-3(b), method M-2026.1, quoted“Exposed reinforcement without recorded section loss does not of itself reduce item 62 below 6. Where section loss is recorded, or where CS3 exceeds ten per cent of the assessed quantity, it does.”
| Item | Rating | Basis |
|---|---|---|
| Barrel | 6 | CS3 3.6 % of assessed; exposed bars, no section loss; 3.0 m not assessed |
| Headwalls | 7 | joint sealant loss 1.10 m at one junction; no concrete defect |
| Wing walls | 8 | no recorded defect |
| Waterway adequacy | 7 | sand accumulation at the inlet apron, 0.30 m; barrel clear over the assessed length |
| Traffic safety features | meets | barriers and end treatments present and undamaged at the site visit |
Two ratings can legitimately say different things about one structure: the index measures extent-weighted condition; the component rating is governed by the worst significant defect. The report prints both with their bases, so nobody has to choose which one to believe without knowing why they differ.
Output 05 · priced bill of quantities
Logged quantities become paid quantities through a versioned take-off rule, in view, and carry their priority.
Rule TO-04 — break out to 100 mm beyond the sound edge, every side. Take-off rules v3, issued with method M-2026.1.
| Item | Description | From | Qty | Unit | Rate | Amount | Priority |
|---|---|---|---|---|---|---|---|
| 04.21 | Concrete repair, patch to sound substrate, ≤ 50 mm | D-02, D-03 | 0.69 | m² | 1,450 | 1,000.50 | High |
| 04.05 | Reinforcement cleaning and passivation | D-03 | 0.84 | m | 520 | 436.80 | High |
| 09.30 | Joint sealant renewal, headwall to wing wall | D-05 | 1.10 | m | 260 | 286.00 | Medium |
| 06.12 | Crack injection, epoxy, ≥ 0.3 mm | D-01 | 5.40 | m | 420 | 2,268.00 | Low |
| 07.15 | Reinstate slope protection: backfill, compact, grouted rip-rap | D-08 | 6.00 | m² | 140 | 840.00 | Low |
| 12.02 | Remove sand and debris from inlet apron, dispose | D-07 | 9.84 | m³ | 45 | 442.80 | Service |
| 11.04 | Dewater and clean cell 2 for inspection | D-06 | — | — | — | prov. | Service |
| Subtotal, items taken | 5,274.10 | ||||||
Preliminary. Quantities derive from the defect log through the take-off rule named in each row, not through judgement applied at the time of pricing. This is an order of cost for capital planning and prioritisation; it is not a tender price, it is not a design, and it is superseded by the engineer’s signed version at sheet 09.
Output 06 · depreciated replacement cost
The value is the index applied to a stated replacement cost — and the route that cannot be computed says so.
| No | Item | Unit | Quantity | Unit rate | Amount |
|---|---|---|---|---|---|
| 1 | Road works over the culvert, full depth | m² | 468.00 | 340.00 | 159,120.00 |
| 2 | Two-cell reinforced concrete box culvert, 2 × (3.0 × 2.4) m | m | 18.00 | 11,500.00 | 207,000.00 |
| 3 | Headwalls and wing walls | m² | 102.56 | 900.00 | 92,304.00 |
| 4 | Apron slabs, inlet and outlet | m² | 65.60 | 450.00 | 29,520.00 |
| Current replacement cost, CRC | 487,944.00 | ||||
Output 07 · recommendations, preservation options and the deferral case
What to do, by when, what each option assumes — and what deferral costs in present value.
| Priority | Timing | Items | Amount |
|---|---|---|---|
| High | within 3–6 months | 04.21 patch repair · 04.05 reinforcement passivation (D-02, D-03) | 1,437.30 |
| Medium | within 6–12 months | 09.30 joint sealant renewal (D-05) | 286.00 |
| Low | before the next biennial inspection | 06.12 crack injection (D-01) · 07.15 slope protection (D-08) | 3,108.00 |
| Service | when possible | 12.02 clear inlet apron (D-07) · 11.04 dewater cell 2, provisional (D-06) | 442.80 + prov. |
| Items taken | 5,274.10 | ||
A
No works this cycle. Re-inspect at the next programmed cycle, 24 months.
Assumesan unprotected soffit spall with exposed reinforcement continues to open over the method’s stated interval, and that item 04.21 grows with it.
B
All items taken, in the priority order of Table 9.1.
Assumesnothing further. Returns the assessed elements to CS1 and CS2. The cell 2 invert and the inlet apron slab stay unassessed until cleared; no option changes a state that was never observed.
C
B, with 11.04 taken: dewater cell 2, clear the inlet apron, and inspect the remaining 3.00 m and 32.8 m² to the protocol.
Assumesaccess can be arranged within the cycle. The quantity for 11.04 is established on access and not before.
The preservation case — repair now, or defer
The preservation argument, computed rather than asserted. Deferring a repair does not save its cost; it moves a larger cost nearer. What follows is the barrel, the element that carries the high-priority defect: what it is worth in present value to do each repair now, against doing nothing — under the method’s own curve, its own treatment effects, and its own discount rate, each cited below. On this element a patch costing 1,000.50 stands against 201,181.02 to 249,611.66 of present value — not a saving claimed as fact, but what the method’s curve and rate imply.
| Scenario | Cost now | Remaining life | Present value | Against no repair |
|---|---|---|---|---|
| A · no repair | nil | 3–5 y | 401,054.40 – 433,780.44 | — |
| B · 04.21 patch repair High | 1,000.50 | 19–30 y | 151,442.74 – 232,599.42 | 201,181.02 – 249,611.66 |
| B · 06.12 crack injection Low | 2,268.00 | 19–30 y | 152,710.24 – 233,866.92 | 199,913.52 – 248,344.16 |
How the comparison is pairedThe long life of one scenario against the long life of the other, the short against the short — never the optimistic end of one against the pessimistic end of the other, which would flatter whichever side the pairing was chosen to favour. The repair’s own cost is already inside its present value, so each figure in the last column is net of paying for the repair.
What the method does not state, this page does not print. There is no cost-growth rule for a deferred patch, so no grown repair price appears here. What deferral changes in this table is the date of the replacement, not the price of the patch — and that alone is the whole of the case.
ISNAD presents the options and the assumption behind each. The engineer chooses, and the choice is recorded against the version they sign. No option is marked recommended, and the option to do nothing is set in the same weight as the others.
Output 08 · evidence-linked report and inspection certificate
Every rendered line resolves to a measurement, a plate and a decision — and the certificate carries the same figures.
— 14 —
Citations annex
| Mark | Cites | Evidence | Confirmed by | On |
|---|---|---|---|---|
| 1 | D-01 | tape 5.40 m, gauge 0.4 mm · plate 25-118, region A | Engineer of record | 11.02.2026 |
| 2 | D-02, D-03 | tape 0.95 × 0.40 m, bars 0.84 m · plate 25-121, regions A and B | Engineer of record | 11.02.2026 |
| 3 | D-04 | tape 1.80 × 0.60 m · plate 25-126, region A | Engineer of record | 11.02.2026 |
| 4 | D-06 | no measurement, no plate — cell 2 invert submerged at the site visit | Engineer of record | 11.02.2026 |
4 marks · 0 figures in the extract above without one
Structure inspection certificate
Certificate CU-014 / 2026-01 · issued under method M-2026.1 · version 3 of the report
A clause that cannot resolve to a measurement and a plate is not rendered. The certificate prints nothing the report does not carry, and what could not be done is on it at the same standard as what was.
Output 09 · signed method version
Two signatures. Two liabilities.
Signed by ISNAD. Condition-state calibration, significance factors, take-off rules, the repair catalogue, the rating table and the dated rate basis are versioned, append-only, and citable in a contract by version and hash.
ISNAD · author of the method
Signed by the engineer of record. Their judgement governs every figure on these sheets. A correction does not edit this version; it issues the next one, and this one stays exactly as it was.
Engineer of record · this version only
A report cites the method version it was produced under. That is the whole of the attribution: a figure, the measurement it rests on, the rule that produced it, and the two people accountable for each.
Six stations, from the site to the signature.
01
Define
Select the structure type and configuration. ISNAD instantiates a provisional element kit, corrected during the site inventory pass.
02
Capture
Follow a guided protocol for every required element and face. Record scale, coverage, inaccessible areas and image quality before leaving the site.
03
Read & measure
Propose visible defects on known elements, reconcile overlapping photographs and measure their extent locally from a recorded scale source.
04
Rate
Apply the signed ISNAD Method to confirmed observations and explicit coverage denominators. Present the condition-state distribution and applicable rating for engineer review.
05
Price & preserve
Convert confirmed quantities through versioned take-off rules, the repair catalogue and dated rates into a preliminary BoQ and preservation options.
06
Report & sign
Prepare the required report with evidence citations and the applicable method-version hash. The engineer corrects and signs an immutable version.
Comparison is not a station
When history exists, ISNAD adds comparison. When it does not, the method creates the baseline. Earlier cycles are an input where they exist; a structure with no previous inspection is the normal starting condition, and the method — not the history — produces the rating, the quantity and the price.