Worked example · one fictional culvert

The worked example.

One fictional culvert, carried from a site visit to a signed report and certificate — every output shown, every figure checkable with a pencil.

What is produced

Nine outputs, each on a sheet below.

Shown on nine sheets below, in the order a report carries them. Everything is one fictional culvert, carried from one site visit to a signed report and certificate.

  1. 01Structure inventory — dimensions and element quantitiessheet 01
  2. 02Defect log with sketch — measured on sitesheet 02
  3. 03Element condition table and structure condition indexsheet 03
  4. 04Structure rating and component ratingsheet 04
  5. 05Priced bill of quantities with repair prioritiessheet 05
  6. 06Asset valuation — depreciated replacement costsheet 06
  7. 07Recommendations, preservation options and what deferral costssheet 07
  8. 08Evidence-linked report and inspection certificatesheet 08
  9. 09Signed method versionsheet 09

Condition inspection report — worked example

CU-014 · Wadi crossing culvert · two-cell reinforced concrete box · 2 × (3.0 × 2.4) m cells · 18.0 m barrel

Structure
Drainage culvert under a dual carriageway · inlet and outlet headwalls, four wing walls, apron slabs both ends
Site visit
11.02.2026 · routine visual inspection · one engineer, one assistant
Inputs
as-built drawing set AB-014 (2019) · tape, laser and crack-gauge measurements · 41 photographs, each with a scale reference
Method
ISNAD Method M-2026.1 · culvert element set · schedule of rates RS-2026-Q1
Data
Fictional throughout. No client material, no client photograph and no real structure appears on this page.
ISNAD · CU-014 condition inspection · fictional asset Worked example Sheet 01 / 09
01Sheet 01 / 09 · inventory

Output 01 · structure inventory

Every quantity has a source: the as-built drawing, or a measurement taken on site.

The inventory pass walks the structure from the road level over the culvert to the inlet and then the outlet. Dimensions are read from the as-built set and checked by tape and laser on site; where the two differ, the site figure governs and both are recorded. What could not be reached is written down before anything is rated: the inlet apron lay under sand and three metres of cell 2 stood under approximately 0.4 m of standing water.

Identification

Structure
CU-014 · drainage culvert
Carries
dual carriageway, 2 × 3 lanes
Crosses
wadi channel, ephemeral
Coordinates
recorded on site · withheld here
Year built
unknown — no record
As-built
available · set AB-014, 2019

Configuration

Barrel
2 cells · 3.00 × 2.40 m · 18.00 m long
Headwalls
inlet and outlet · 8.20 × 3.40 m
Wing walls
A, B inlet · C, D outlet · 4.50 × 2.60 m
Apron slabs
inlet and outlet · 8.20 × 4.00 m
Previous cycle
none in the register — baseline
Table 2.1 — element quantities and their source
ElementQuantityMeasured asSource
Barrel, both cells36.0 m18.00 m × 2 cells, length along flowAB-014 sh. 3 · tape 18.02 m
Headwalls55.76 m²2 × (8.20 × 3.40 m), exposed faceAB-014 sh. 4 · tape, agrees
Wing walls A–D46.80 m²4 × (4.50 × 2.60 m), mean heightlaser, on site · AB-014 sh. 4
Apron slabs65.60 m²2 × (8.20 × 4.00 m)AB-014 sh. 3 · outlet taped; inlet under sand
Embankment slopes120.0 m²2 × 60 m², protected slopeAB-014 sh. 5 · paced on site
Wearing surface over468.0 m²26.0 m carriageway × 18.0 mAB-014 sh. 2

Quantities are estimated from the as-built drawings and confirmed or corrected by site measurement, and the report says which. A quantity with neither source is not printed.

02Sheet 02 / 09 · defect log

Output 02 · defect log and sketch

Every defect is located on the sketch, measured on site, and tied to the plate that shows it.

INLETOUTLET PLAN · DIMENSIONS IN METRES ABCD D-07SAND APRON CELL 1CELL 2 NOT ASSESSED D-01D-02 · D-03D-04 D-06D-05D-08 18.003.003.00 CH. 0 AT INLET FACE · D-01 CH. 4.2–9.6 · D-02 CH. 7.8 · D-04 CH. 11.2–13.4 · D-06 CH. 15.0–18.0
Fig. 1 — defects sketch, plan. Line work set in the browser; hatched, copper: not assessed.
Table 3.1 — defect log, site visit 11.02.2026
RefElement · locationDefectLengthWidthQuantityStatePrio.Plate
D-01Barrel · cell 1 soffit, ch. 4.2–9.6Cracking, transverse, 0.4 mm gauge5.40 m—5.40 mCS2Low25-118
D-02Barrel · cell 1 soffit, ch. 7.8Spalling to reinforcement0.95 m0.40 m0.38 m²CS3High25-121
D-03Barrel · within D-02Exposed reinforcement, 2 bars, no section loss recorded0.84 m—0.84 mCS3High25-121
D-04Barrel · cell 2 wall, joint J3, ch. 11.2–13.4Efflorescence at construction joint1.80 m0.60 m1.08 m²CS2Low25-126
D-05Headwall · junction with wing wall C, outletJoint sealant loss1.10 m—1.10 mCS2Medium25-133
D-06Barrel · cell 2 invert, ch. 15.0–18.0Not assessed — submerged, approx. 0.4 m3.00 m————none
D-07Apron slab · inletSand accumulation, 0.30 m deep; slab beneath not assessed8.20 m4.00 m9.84 m³—Service25-104
D-08Embankment · inlet, left of wing wall AErosion of slope protection3.00 m2.00 m6.00 m²CS2Low25-109

Length and width are taken on site by tape; crack width by gauge. Quantity is length × width where both apply, and the unit follows: metres for a line, square metres for an area, cubic metres where a depth was measured (D-07). D-02 was proposed from the plate at 0.41 m² and corrected by the engineer to the taped 0.38 m²; the proposal is kept beside the correction, not overwritten.

Plate 25-121 · cell 1 soffit · ch. 7.8 · D-02, D-03

Captured
11.02.2026 · walkthrough, cell 1
Scale
100 mm target on rib R4, in frame — a check on the tape, not a substitute for it
Regions
A — spall · B — exposed bars
Cited at
Table 3.1 · Table 4.1 · rule CS-3(b) · annex marks 2 and 3

Photograph withheld. ISNAD does not publish an owner’s images — not in a specimen, not in marketing, not anywhere outside the owner’s own record. What leaves the instrument is the citation: plate, element, chainage, region, and the measurement it supports.

03Sheet 03 / 09 · condition index

Output 03 · element condition table and structure condition index

The calculation is printed in full, so the index can be checked from the table that produced it.

Barrel · CS3 poor 1.2 m · CS4 severe 0.0 m, drawn at zero width rather than omitted · after the gap, hatched: not assessed 3.0 m

Barrel, reconciled to the logD-01 runs 5.40 m. The 1.20 m length containing D-02 and D-03 is taken at CS3, so D-01 contributes 4.20 m to CS2 and no length is counted twice; D-04 adds 1.80 m at CS2. Assessed 33.0 m: CS1 25.8, CS2 6.0, CS3 1.2. The states sum to the assessed quantity, never to the element total.

Table 5.1 — structure condition calculation, method M-2026.1
ElementCS1CS2CS3CS4WCSESCISiSi × ESCI
Barrel78.2 %18.2 %3.6 %0.0 %1.25491.5 %4.0366.0
Headwalls96.1 %3.9 %0.0 %0.0 %1.03998.7 %2.0197.4
Wing walls A–D100.0 %0.0 %0.0 %0.0 %1.000100.0 %1.0100.0
Apron slabs (outlet assessed)100.0 %0.0 %0.0 %0.0 %1.000100.0 %1.0100.0
Embankment slopes95.0 %5.0 %0.0 %0.0 %1.05098.3 %1.098.3
Wearing surface100.0 %0.0 %0.0 %0.0 %1.000100.0 %1.0100.0
Σ10.0961.7
Structure condition indexSCI = Σ(Si × ESCI) / ΣSi = 961.7 / 10.096.2 %
WCS
Weighted condition state, Σ(state × share): the share-weighted mean state of the element.
ESCI
Element condition index, 100 × (4 − WCS) / 3 on a four-state scale — 100 % when everything is CS1.
Si
Significance factor of the element in the structure, from the method’s culvert element set; the barrel carries 4.0 of the 10.0.
Denominator
Each element’s shares are of its assessed quantity. The inlet apron and 3.0 m of cell 2 are excluded, not assumed sound.
04Sheet 04 / 09 · ratings

Output 04 · structure rating and component rating

Two ratings from one evidence base — and the rule that produced each, quoted.

96.2%

Structure condition index · band

Very good

Band 90–100 in the method’s rating table: minor defects in secondary elements; routine maintenance. The barrel’s spall is inside that band because its extent is 3.6 % of the assessed length.

6

NBI item 62 — culvert · component rating

Satisfactory

“Structural elements show some minor deterioration.” Governed by the worst significant defect, not by its extent: exposed reinforcement holds the item at 6 under rule CS-3(b).

Rule CS-3(b), method M-2026.1, quoted“Exposed reinforcement without recorded section loss does not of itself reduce item 62 below 6. Where section loss is recorded, or where CS3 exceeds ten per cent of the assessed quantity, it does.”
Table 6.1 — element and appraisal ratings, as the certificate carries them
ItemRatingBasis
Barrel6CS3 3.6 % of assessed; exposed bars, no section loss; 3.0 m not assessed
Headwalls7joint sealant loss 1.10 m at one junction; no concrete defect
Wing walls8no recorded defect
Waterway adequacy7sand accumulation at the inlet apron, 0.30 m; barrel clear over the assessed length
Traffic safety featuresmeetsbarriers and end treatments present and undamaged at the site visit

Two ratings can legitimately say different things about one structure: the index measures extent-weighted condition; the component rating is governed by the worst significant defect. The report prints both with their bases, so nobody has to choose which one to believe without knowing why they differ.

05Sheet 05 / 09 · bill of quantities

Output 05 · priced bill of quantities

Logged quantities become paid quantities through a versioned take-off rule, in view, and carry their priority.

D-02 · taped on site0.95 × 0.40 m = 0.38 m²
→
Paid1.15 × 0.60 m = 0.69 m²

Rule TO-04 — break out to 100 mm beyond the sound edge, every side. Take-off rules v3, issued with method M-2026.1.

Table 7.1 — bill of quantities, schedule RS-2026-Q1
ItemDescriptionFromQtyUnitRateAmountPriority
04.21Concrete repair, patch to sound substrate, ≤ 50 mmD-02, D-030.69m²1,4501,000.50High
04.05Reinforcement cleaning and passivationD-030.84m520436.80High
09.30Joint sealant renewal, headwall to wing wallD-051.10m260286.00Medium
06.12Crack injection, epoxy, ≥ 0.3 mmD-015.40m4202,268.00Low
07.15Reinstate slope protection: backfill, compact, grouted rip-rapD-086.00m²140840.00Low
12.02Remove sand and debris from inlet apron, disposeD-079.84m³45442.80Service
11.04Dewater and clean cell 2 for inspectionD-06———prov.Service
Subtotal, items taken5,274.10
Rates
Schedule RS-2026-Q1, dated 05.01.2026, in the owner’s currency — a specimen schedule, fictional. Excludes access, traffic management and provisional items.
D-04
No item. Efflorescence at CS2 is recorded and monitored; the catalogue holds no repair for it at this state.
11.04
No quantity, because none has been established. Three metres of cell 2 were not assessed.

Preliminary. Quantities derive from the defect log through the take-off rule named in each row, not through judgement applied at the time of pricing. This is an order of cost for capital planning and prioritisation; it is not a tender price, it is not a design, and it is superseded by the engineer’s signed version at sheet 09.

06Sheet 06 / 09 · asset valuation

Output 06 · depreciated replacement cost

The value is the index applied to a stated replacement cost — and the route that cannot be computed says so.

Table 8.1 — current replacement cost, CRC
NoItemUnitQuantityUnit rateAmount
1Road works over the culvert, full depthm²468.00340.00159,120.00
2Two-cell reinforced concrete box culvert, 2 × (3.0 × 2.4) mm18.0011,500.00207,000.00
3Headwalls and wing wallsm²102.56900.0092,304.00
4Apron slabs, inlet and outletm²65.60450.0029,520.00
Current replacement cost, CRC487,944.00
By conditionCRC × SCI = 487,944.00 × 96.2 %469,402.13
By remaining lifeCRC × RUL / EUL — year built unknownnot computable
Depreciated replacement costby condition, stated as such469,402.13
Rates
Replacement rates from schedule RS-2026-Q1, the same dated schedule as the bill; quantities from Table 2.1. In the owner’s currency; fictional.
RUL
The year built is unknown (Table 2.1), so the remaining-life route has no input. It is printed as not computable, not estimated — an age assumed here would become a value on a balance sheet.
Basis
The accounting basis is the owner’s where one exists; the method states the one it used. A valuation is signed as a valuation under that basis, never as a fact about the structure.
07Sheet 07 / 09 · recommendations

Output 07 · recommendations, preservation options and the deferral case

What to do, by when, what each option assumes — and what deferral costs in present value.

Table 9.1 — recommended repairs by priority and timing
PriorityTimingItemsAmount
Highwithin 3–6 months04.21 patch repair · 04.05 reinforcement passivation (D-02, D-03)1,437.30
Mediumwithin 6–12 months09.30 joint sealant renewal (D-05)286.00
Lowbefore the next biennial inspection06.12 crack injection (D-01) · 07.15 slope protection (D-08)3,108.00
Servicewhen possible12.02 clear inlet apron (D-07) · 11.04 dewater cell 2, provisional (D-06)442.80 + prov.
Items taken5,274.10

A

Monitor

No works this cycle. Re-inspect at the next programmed cycle, 24 months.

Assumesan unprotected soffit spall with exposed reinforcement continues to open over the method’s stated interval, and that item 04.21 grows with it.

This cyclenil

B

Repair as scheduled

All items taken, in the priority order of Table 9.1.

Assumesnothing further. Returns the assessed elements to CS1 and CS2. The cell 2 invert and the inlet apron slab stay unassessed until cleared; no option changes a state that was never observed.

This cycle5,274.10

C

Repair, and complete the baseline

B, with 11.04 taken: dewater cell 2, clear the inlet apron, and inspect the remaining 3.00 m and 32.8 m² to the protocol.

Assumesaccess can be arranged within the cycle. The quantity for 11.04 is established on access and not before.

This cycle5,274.10 + 11.04

The preservation case — repair now, or defer

The preservation argument, computed rather than asserted. Deferring a repair does not save its cost; it moves a larger cost nearer. What follows is the barrel, the element that carries the high-priority defect: what it is worth in present value to do each repair now, against doing nothing — under the method’s own curve, its own treatment effects, and its own discount rate, each cited below. On this element a patch costing 1,000.50 stands against 201,181.02 to 249,611.66 of present value — not a saving claimed as fact, but what the method’s curve and rate imply.

PRESENT VALUE OF THE REPLACEMENT EVENT · 4 % REAL · 30-YEAR HORIZON 0100,000200,000300,000400,000 A · NO REPAIRB · 04.21 PATCHB · 06.12 INJECTION
Fig. 2 — present value of the replacement event under each scenario. Solid to the low end of the range, hatched to the high end. Line work set in the browser.
Table 9.2 — repair against deferral, barrel, method M-2026.1
ScenarioCost nowRemaining lifePresent valueAgainst no repair
A · no repairnil3–5 y401,054.40 – 433,780.44—
B · 04.21 patch repair High1,000.5019–30 y151,442.74 – 232,599.42201,181.02 – 249,611.66
B · 06.12 crack injection Low2,268.0019–30 y152,710.24 – 233,866.92199,913.52 – 248,344.16

How the comparison is pairedThe long life of one scenario against the long life of the other, the short against the short — never the optimistic end of one against the pessimistic end of the other, which would flatter whichever side the pairing was chosen to favour. The repair’s own cost is already inside its present value, so each figure in the last column is net of paying for the repair.

Curve
Residence years per condition state from the method’s culvert curve, summed from the present state to end of service. Layer: published curve, engineer-adjusted, not locally calibrated — no local n yet. Specimen.
Treatment
Items 04.21 and 06.12 each return the treated extent to CS1. Specimen, after the FHWA Bridge Preservation Guide (FHWA-HIF-18-022).
Rate
4 % real over a 30-year horizon. Specimen, after the NCHRP Report 483 framework; the owner’s own rate where one is stated.
Governing
The method takes the worst state present as governing, so 3.6 % of the barrel at CS3 carries the whole element at CS3 and its life with it. That is conservative, and it is the rule as written — note that it differs from the index on sheet 03, which weights extent. One measures how much of the element is affected; the other asks how soon the worst of it ends the element’s service. Whether the life rule should instead take the worst state above a stated share is a question for the method, not for this page.
Not combined
Each scenario stands alone. The method states no rule for the combined effect of two treatments, so no combined figure is printed.

What the method does not state, this page does not print. There is no cost-growth rule for a deferred patch, so no grown repair price appears here. What deferral changes in this table is the date of the replacement, not the price of the patch — and that alone is the whole of the case.

ISNAD presents the options and the assumption behind each. The engineer chooses, and the choice is recorded against the version they sign. No option is marked recommended, and the option to do nothing is set in the same weight as the others.

08Sheet 08 / 09 · report and certificate

Output 08 · evidence-linked report and inspection certificate

Every rendered line resolves to a measurement, a plate and a decision — and the certificate carries the same figures.

4.2
Barrel — cell 1. Transverse cracking of 0.4 mm width extends 5.40 m between chainage 4.2 and 9.6 m. A spall of 0.95 by 0.40 m at chainage 7.8 m has exposed two reinforcing bars over 0.84 m; no section loss was recorded. The 1.20 m length containing the spall is taken at condition state 3 and deducted from the cracked length, so that no part of the barrel is counted twice.
4.3
Barrel — cell 2. Efflorescence is present at construction joint J3 over 1.80 by 0.60 m. Three metres of cell 2, between chainage 15.0 and 18.0 m, stood under approximately 0.4 m of standing water and were not assessed. No condition is stated for this length, and it is excluded from the element condition table at § 5.1.

— 14 —

Citations annex

MarkCitesEvidenceConfirmed byOn
1D-01tape 5.40 m, gauge 0.4 mm · plate 25-118, region AEngineer of record11.02.2026
2D-02, D-03tape 0.95 × 0.40 m, bars 0.84 m · plate 25-121, regions A and BEngineer of record11.02.2026
3D-04tape 1.80 × 0.60 m · plate 25-126, region AEngineer of record11.02.2026
4D-06no measurement, no plate — cell 2 invert submerged at the site visitEngineer of record11.02.2026

4 marks · 0 figures in the extract above without one

Structure inspection certificate

Certificate CU-014 / 2026-01 · issued under method M-2026.1 · version 3 of the report

Structure
CU-014 · drainage culvert
Location
recorded · withheld here
Inspection
routine visual · 11.02.2026
Inspector
Engineer of record
Frequency
24 months
Next due
02.2028
Structure index
96.2 % · Very good
Item 62
6 · Satisfactory
Waterway
7 · minor sedimentation
Traffic safety
meets current standards
CRC / DRC
487,944.00 / 469,402.13
Not assessed
cell 2 ch. 15.0–18.0 · inlet apron slab
  • Spalling with exposed reinforcement at one location in the cell 1 soffit; no section loss recorded; repair High priority.
  • Transverse cracking, 0.4 mm, over 5.40 m of the cell 1 soffit; injection before the next inspection.
  • Sand accumulation on the inlet apron, 0.30 m; slab beneath not assessed until cleared.
  • Erosion of the inlet embankment protection, 6.0 m², left of wing wall A.
  • Three metres of cell 2 not assessed — submerged; dewatering provisional.

A clause that cannot resolve to a measurement and a plate is not rendered. The certificate prints nothing the report does not carry, and what could not be done is on it at the same standard as what was.

09Sheet 09 / 09 · signatures

Output 09 · signed method version

Two signatures. Two liabilities.

The method

Document
ISNAD Method · culvert element set
Version
M-2026.1
Issued
12.01.2026
Rule sets
TO v3 · catalogue C-2026.1 · rate set RS-2026-Q1 · rating table RT-2026.1
SHA-256
9f2c41b8 … a7d1 (fictional)

Signed by ISNAD. Condition-state calibration, significance factors, take-off rules, the repair catalogue, the rating table and the dated rate basis are versioned, append-only, and citable in a contract by version and hash.

ISNAD · author of the method

The report

Document
CU-014 · condition inspection report and certificate
Version
3
Frozen
19.02.2026
Produced under
M-2026.1
Signed by
Engineer of record

Signed by the engineer of record. Their judgement governs every figure on these sheets. A correction does not edit this version; it issues the next one, and this one stays exactly as it was.

Engineer of record · this version only

A report cites the method version it was produced under. That is the whole of the attribution: a figure, the measurement it rests on, the rule that produced it, and the two people accountable for each.

The workflow that produces it

Six stations, from the site to the signature.

01

Define

Select the structure type and configuration. ISNAD instantiates a provisional element kit, corrected during the site inventory pass.

02

Capture

Follow a guided protocol for every required element and face. Record scale, coverage, inaccessible areas and image quality before leaving the site.

03

Read & measure

Propose visible defects on known elements, reconcile overlapping photographs and measure their extent locally from a recorded scale source.

04

Rate

Apply the signed ISNAD Method to confirmed observations and explicit coverage denominators. Present the condition-state distribution and applicable rating for engineer review.

05

Price & preserve

Convert confirmed quantities through versioned take-off rules, the repair catalogue and dated rates into a preliminary BoQ and preservation options.

06

Report & sign

Prepare the required report with evidence citations and the applicable method-version hash. The engineer corrects and signs an immutable version.

Comparison is not a station

When history exists, ISNAD adds comparison. When it does not, the method creates the baseline. Earlier cycles are an input where they exist; a structure with no previous inspection is the normal starting condition, and the method — not the history — produces the rating, the quantity and the price.